Our Experiences with Environmental
Assessment:
Selected Case Studies of Environmental
Planning and Assessment Processes in Canada
Prepared By:
The Environmental Planning and
Assessment Caucus of the
Canadian Environmental Network
January 2000
Table of Contents
1.0 Introduction:
What is Environmental Assessment?
What are the core principles of good environmental
assessment?
2.0 Case
Studies: Screenings:
The Sunpine Case
Sulphur Mountain Horse Trail
An Atomic Energy Control Board handling of
screenings
3.0 Case
Studies: Comprehensive Studies:
The TransQuebec and Maritimes
(TQM) Portland Natural Gas Transmission System
(PNGTS) Extension Gas Pipeline Project
4.0 Case
Studies: Review Panels:
Oldman River Dam (EARPGO)
Uranium Mine Tailings Decommissioning (EARPGO)
Nuclear Fuel Waste Management (EARPGO)
The Environmental Assessment of McClean Lake
Cheviot Coal Mine
BHP Diamond Mine
South Kemess Copper / Gold Mining Project
5.0 Case
Studies: Other Processes:
Huckleberry Copper Mine
Bronson Slope Mine Proposal
Licensing of the Maple Leaf Facilities in
Brandon
The British Columbia Salmon Aquaculture Review
APPENDIX:
REFERENCES AND SOURCES

1.0 Introduction
Environmental Assessment
in Canada takes many shapes and forms. Canada
has a federal EA process, governed by the Canadian
Environmental Assessment Act, ten distinct
provincial assessment processes, territorial processes,
a number of EA bilateral agreements between the
provinces and the federal government, and different
EA processes for projects undertaken by Crown
Corporations, Port Authorities, on First Nations
lands, among others. With all of these processes
added together, Canada might have as many as 200
EA regimes (Nikiforuk, 1997). The process of EA
can and does take place in many different
ways at different levels of government.
There are, however, some underlying
"core" principles that should be part of all Environmental
Assessments. In this report, the core principles
of good, effective EA are outlined, and then a
number of case studies of EA "in action" are presented.
The case studies range from considering the implications
of the absence of any EA in the licensing
of the Maple Leaf Facilities in Brandon, Manitoba,
to the very detailed assessments of larger mining
projects such as the Cheviot coal mine in Alberta
and the BHP diamond mine in the North West Territories.
Each case study has been prepared
by a member of the Environmental Planning and
Assessment Caucus. The Environmental Planning
and Assessment Caucus is a national group of "member
groups" housed within the Canadian Environmental
Network. The Caucus is made up of activists, community
educators, ecological foresters, lawyers, and
concerned citizens, among others, all of whom
have first-hand experience with EA in Canada.
Additionally, all have an interest in improving
environmental planning and assessment in Canada
at local, provincial and national levels while
working to broaden citizen participation in these
processes.
Caucus members have brought different
voices to each of their narratives included in
this report. They have also chosen to highlight
different aspects of what they feel to be the
strengths and weaknesses apparent in the EA in
which they were involved.
This compilation of case studies
comes at a crucial time for EA in Canada. Not
only are bi-lateral agreements for EA being put
into place between federal and provincial powers
under the Canada-Wide Accord on Environmental
Harmonization, the Canadian Environmental
Assessment Act is up for review beginning
January 2000. These case studies highlight many
of the weaknesses, and some of the strengths,
of the current practice of EA in Canada. The Review
of the Act is an excellent time to address inherent
weaknesses and build on and enhance strengths.
What is environmental assessment?
Environmental Assessment is
an approach to planning...At minimum, environmental
assessment is a means of anticipating and avoiding
or reducing problems before they arise. More positively,
it is a broader and more far-sighted approach
to determining what actions we should take to
make the best of our opportunities (Gibson, 1993).
EA is a process...
Environmental assessment
is the process of examining the impact of an activity
a project, a program or a policy on the
entire environment it will potentially affect.
An ideal EA is proactive and anticipatory and,
as a decision-making process, fully integrated
into the development of a project, program or
policy. The ideal EA process will require integration
of environmental consideration in initial planning,
where needs and alternative responses to such
needs are addressed (Gibson, 1992).
EA is a tool...
When done properly, EA is
a democratic decision-making tool used to determine
whether an undertaking has social, economic and
ecological value for the health of those areas
and people potentially affected by a proposed
project, program or policy. EA provides a framework
within which governments, industry and the public
can make informed and socially and ecologically
acceptable decisions.
EA can save time and
money...
EA is sometimes seen as a
hindrance to development or competitiveness. While
EA clearly costs money and takes time to perform,
the amount of money spent or the amount of time
taken to do a good, comprehensive EA’s are usually
substantially smaller than after-the-fact rehabilitation
or project alteration costs. Done properly, EA
is a valuable process, saving money and time while
ensuring sensible decision making.
EA is dynamic...
EA is a constantly evolving
process. This evolution can largely be credited
to the interventions of Canadian citizens and
groups concerned about government and industry
decision-making. The work and energy of concerned
citizens has contributed to landmark decisions
that have shaped and defined the process, application
and use of EA. The Kemano Completion Project,
the Oldman River Dam, the Rafferty-Alameda Dams
and the Great Whale Hydroelectric Project were
either stopped or significantly modified by the
determined efforts of citizens, landowners, environmental
groups and Aboriginal peoples.
What are the core principles
of good environmental assessment?
If we understand the core
principles of an ideal EA, we are in a better
position to see the strengths and weaknesses of
EA as it is practiced on the ground. The following
principles would be seen in an ideal EA. This
is not necessarily how EA is actually carried
out across Canada.
EA should be an open, accountable
and independent process.
Good EA is open, transparent
and accountable, and administered by a neutral
and independent body. A process that is not open
and transparent is of no benefit to the public,
government, or the proponent. A process that is
administered by a body with a vested interest
in the project is not credible.
An open process is
one which is easily and fairly accessible to
affected parties, and one where parties have
an opportunity for meaningful involvement in
decision-making.
A transparent process
is one in which the details of why and how decisions
were made are clear to everyone involved. All
information and factors that directed the decision
making process are clear, on the table, and
accessible to anyone interested.
An accountable process
is one in which lines of decision-making are
clear, and decision-makers acknowledge responsibility
for the decisions they have made.
EA should be done early
and before any decisions are made and address
needs and alternatives at this early stage.
The impact of a project,
plan or policy should be considered as early as
possible in the design and planning of the project
and before any decisions are made regarding the
project. Waiting too long before assessing the
project can cause unnecessary time and financial
costs to both the public and the proponent and
can cause project delays. If an assessment is
done after decisions are made that favour the
project, the assessment might not be an objective
one.
More importantly, EA should be
initiated while the need for the project and alternatives
to fill that need are still open for consideration.
Only at this point can best options be selected
on environmental as well as technical and
financial grounds.
EA should apply to every
undertaking that may have environmental significance.
EA should be applied
to all public and private projects, policy and
plans that may be environmentally significant.
An approach that considers only reviewing those
projects, policies and plans that are defined
in regulations found in EA law, allows many projects,
plans and policies to slip through the cracks
and not be assessed.
Environment should be defined
broadly in an EA.
In addition to including
the biophysical effects and impacts of a project,
plan or policy, environment should be defined
in EA law to include the social, economic, spiritual
and cultural impacts. Many programs and projects
have significant immediate and future impacts
on local, regional and global ecosystems and on
community health, livelihood, traditional practices
and autonomy. If environment is defined too narrowly
in the law, these impacts will not be taken into
consideration during the EA.
The public should be involved
in a significant and effective way.
It is important that
the public have an opportunity to participate
in EA in a significant and effective way. This
involves access to information and expertise when
needed; access to funding so the public can organize,
learn about the project / options / issues and
formulate positions and present concerns effectively;
and timely notification of the steps in an EA
so that the public has the time to respond to
documents or studies.
EA should result in a binding
decision.
The ultimate decision that
arises from the EA process should be binding on
the decision-makers that give the final decision
concerning the undertaking.
EA should be efficient
and integrated with other planning processes.
Ideally, EA should
be just one part of a comprehensive environmental
planning framework. This framework should: define
regional environmental goals, objectives and priorities;
inform policy development and review; incorporate
environmental consequences and values into development
decisions; and monitor progress against goals
and objectives.

2.0 Screenings
The Sunpine Case
Overview
In 1993, Friends of the West
Country (FWC) , a non-governmental organization
that focuses on the impacts of timber harvesting,
became aware that Sunpine Forests Products (Sunpine)
was planning on building an all-season " trunk"
road that would allow the company to access an
area they planned to harvest under their Forest
Management Agreement. Building the all-season
road required the construction of two bridges
over the Ram and Prairie Creeks. Individuals involved
in FWC live in the area and use the land for hunting,
fishing, trapping, and recreational purposes,
and they wanted to ensure that the environmental
effects of the proposal were understood and public
concerns fully considered before any irrevocable
decisions were made regarding the proposed bridges.
Between late Fall 1993 and August
1996, various requests were made to the Department
of Fisheries and Oceans (DFO) and the Canadian
Coast Guard (CCG – the responsible authorities)
by the FWC for impact assessments, information
and clarification on numerous issues. Among other
things, the letters pointed out the likelihood
of increased siltation of streams crossed by the
proposed road, increased sediment run-off into
streams following rain events and fragmentation
of wildlife habitat. The FWC were denied access
to the Sunpine application document, citing lack
of resources to copy the application for distribution
and were instructed to go to the public registry
for any pertinent documents related to the case
in Sarnia, Ontario. Although finally provided
with a small number of relevant documents, FWC
were told that they would have to go through a
lengthy "Access to Information Act" process to
get any others they were not given.
The result of the three-year
process was the approval of the Screening process
by the CCG, which looked only at the environmental
effects of the two bridges but failed to take
into account impacts from all "related undertakings"
(Section 15, Canadian Environmental Assessment
Act – hereafter CEAA) and to consider the project’s
"cumulative effects" (Section 16 [1] CEAA). Two
weeks later, the CCG had completed an addenda
to the Screening Reports and then proceeded to
recommend the issuance of Approvals under the
NWPA. Approvals were granted the following day.
On August 19, 1996, FWC decided
to take the matter to court and filed an "Originating
Notice of Motion" with a supporting affidavit.
The FWC argued that the CCG had not complied with
the requirements of the CEAA, particularly Sections
15 and 16 (see above) and Sections 18 (3) and
55 which stipulate that a public registry must
be provided that is convenient and must give the
public an opportunity to examine and comment on
any records in the registry.
On July 7, 1998, Justice J. Gibson
of the Federal Court, Trial Division, decided
that the CCG failed to comply with CEAA by arbitrarily
limiting their environmental review to the impacts
of the two bridges. The Judge ruled that the CCG
and Minister of DFO failed to assess the cumulative
impacts of the project in combination with other
projects and activities in the area as required
by law. Justice Gibson also stated that Sarnia,
Ontario did not constitute "convenient public
access" to documents in the public registry for
residents of the "foothills of Alberta".
On September 25, 1998, the Government
of Canada asked for an expedited appeal before
the Federal Court of Appeal as well as a stay
of the ruling until the issue was resolved in
the Court of Appeal. In a press release, the Government
stated, "The Government is appealing to clarify
an important point of law. We need a clear understanding
of the discretion federal departments may exercise
in determining the scope of projects and assessments
under the CEAA" (Justice Minister Anne McLellan).
In November, 1998, Federal Court
Chief Justice Isaac dismissed the stay and stated
that a new environmental assessment must be undertaken.
The appeal was expected to be heard in the late
spring or early summer of 1999.
Key Issues
Triggering:
The Federal Government took months
to decide whether or not there was a federal trigger
that would force them to conduct an environmental
assessment under CEAA. Although there was ample
evidence of public concern, uncertainty of impacts,
and potential damage to fisheries habitat, the
federal government did not undertake the screening
process until 1996, three years after FWC became
aware of the company’s plans to build the road.
This late triggering only caused unnecessary delays
and uncertainty for the proponent, as well as
denying the right for the public to be involved
in the decision making process.
Public Involvement:
The overview above also highlights
the obstacles faced by the public when they tried
to obtain documents pertinent to the project.
FWC were even told that they had to contact the
proponent to receive a copy of the Sunpine proposal
document itself. Later, there were numerous pre-trial
motions that forced document production which
resulted in a May 1997 preliminary judgment against
the federal government by Justice Muldoon of the
Federal Court. This decision was appealed by the
federal government, where they were once again
unsuccessful. Justice Gibson, in his later ruling,
stated that the DFO’s handling of document requests
was "completely inappropriate and more importantly
not in keeping" with CEAA.
Consideration of Cumulative
Effects:
It is important to note that
the FWC, along with foresters and biologists with
the Alberta Department of Environment, identified
a number of potential cumulative effects that
were excluded from consideration in the screening,
thereby severely limiting the CCG’s ability to
make an informed decision in this case. They included:
- Increased siltation of streams due to road
crossings and associated fills and ditches
- Increased run-off of sediments into streams
following rain events resulting from the road
and logging activities near streams
- Increased harvest of fish and wildlife in
the areas because of greater access from the
new road
- Increased human presence in the area, due
to the road, with resulting negative impacts
on some wildlife species
- Fragmentation of wildlife habitat by the road
and logging activities
- A range of fishery-related impacts from logging,
including: physical deterioration of streambanks
and channels; increased nutrient loads and water
temperature; barriers to fish passage; loss
of vegetation on streambanks; and the effect
of widespread forest removal on streamflow.
Sulphur Mountain Horse
Trail
Overview
Environmental screenings under
the Canadian Environmental Assessment Act are
frequently conducted in National Parks. These
projects are often in close proximity to one another
and interact with tourism activity occurring in
a large area. This project, in Banff National
Park, involved a proposal by Parks Canada to relocate
a horse trail in order to protect a critical wildlife
movement corridor.
The need for the project arose
when existing hiking and horse trails were closed
to secure an existing wildlife movement corridor
around the Town of Banff. Securing the corridor
at the base of Sulphur Mountain was recommended
in the environmental screening of the Middle Springs
II area structure plan. Unfortunately the environmental
assessment did not assess the effects of closing
the trails; the subsequent need for two-way horse
traffic overwhelmed the trails designed for one-way
movement.
A proposal to build new trails
was made by Parks Canada. Alternative new trail
routing options had the potential to affect: the
habitat of an endangered snail found nowhere else
in the world; an historic site; environmentally
sensitive wetlands; as well as existing public
road and walking path alignments. The direct involvement
of a federal authority and federal lands triggered
an environmental assessment of the proposal under
the Canadian Environmental Assessment Act (CEAA).
Since the required trail construction
was to be on National Park land, Parks Canada
served as both proponent and responsible authority.
In addition, Parks Canada staff specializing in
environmental assessment prepared the assessment
and allowed 14 days for public review after notifying
parties known to be concerned. Upon receiving
public comments a site meeting was held to discuss
comments on the EA and to examine the sites affected
by the project. A number of local researchers
and a local naturalist club commented on the project
and were invited by Parks Canada to the site visits
along with the trail ride operator and various
Parks Canada staff members.
The environmental assessment
recommended building a new horse trail within
the sensitive wetlands. It was stated that this
option would address the issues of quality of
experience and public safety while avoiding public
road crossings and the endangered snail habitats.
By redeveloping an abandoned berm through the
sensitive wetland, this option was predicted to
involve minimal disturbance and to have lower
construction costs.
Public comments on the EA agreed
with the identification of most environmental
issues but they were very concerned that Parks
Canada had not addressed the longer term planning
issues. Public reviewers were also concerned that
all viable alternatives had not been considered.
Other public concerns related to the project included
a desire to protect the integrity of the sensitive
wetlands according to the Banff National Park
Management Plan. The public expressed a need to
postpone the project until a local management
plan required by the Banff National Park Management
Plan could be developed.
As a result of the comments received,
Parks Canada facilitated a site visit to discuss
the project. Following the discussion it was recommended
that a new preferred alternative be adopted. This
option involved twinning an existing trail along
the edge of the wetlands to allow for safe two-way
horse traffic. While this option required some
additional disturbance, it avoided fragmentation
of the wetlands which would have occurred if the
preferred option had proceeded.
Key Issues
Consideration of Alternatives:
Consideration of alternative
alignments for the proposed trail is a key feature
of this assessment. Each of the potential options
was clearly explained and analysed in the screening
report according to the effects that each option
had the potential to generate. This documentation
of the analysis made it possible for reviewers
to understand the environmental tradeoffs considered
in selecting the preferred option. As a result,
public discussion of the screening report focused
on resolving key issues. Since the assessment
process already was open to the consideration
of alternatives it was possible to select a new
alternative following public review. However,
while this assessment was to be praised for its
consideration of alternatives there was serious
concern that an apparently obvious alternative,
and the one having the least serious environmental
effects, was not considered. Direction given to
EA practitioners (in legislation or EA standards
of practice) must be more specific to ensure that
all potentially viable alternatives are assessed.
Public Comment/Participation:
This case demonstrates how public
comment on a relatively small project improved
the EA outcome. Revaluation of the project based
on public input resulted in the selection of a
new option which improved protection of the natural
environment while continuing to address the socio-economic
issues. Public involvement improved communication
among the interested parties and improved transparency
of the decision-making process.
However: 1) Very few copies of
the screening report were printed. One copy was
available for review at the Parks Canada administration
building in Banff. Park staff loaned another personal
copy for review; 2) The fact that screening level
EA in the area regularly depends on and benefits
from public participant experience and expertise
suggests that participant funding of some nature
could have helped to compensate the effort, time
and expenses the public participants regularly
commited to improving planning through EA processes;
finally, 3) The review time should have been longer
to allow for detailed review. A more general notification
would have allowed other key interested parties
such as the Town of Banff to respond. Also, scheduling
the site visit in the middle of a work day limited
public participation.
Improved Planning:
A critical issue raised by the
interested parties was the need to place this
project in the context of an overall plan for
the Sulphur Mountain area. While this assessment
was completed without the benefit of an area plan,
the issues raised and discussed provided stimulus
for Park managers to begin taking action towards
the preparation of that plan.
The earlier Middle Springs II
screening report should have been more diligent
in the assessment of effects and alternative approaches
to design and implementation of the closure. Such
early consideration would have allowed planners
more flexibility in addressing the issues of trail
safety and reduced quality of park experience
resulting from congestion created by a mitigative
measure recommended in that assessment.
An Atomic Energy Control
Board handling of screenings
Overview
The project in question was the
proposed expansion of the tailings management
facility (TMF) of the Cluff Lake Uranium Mine
in northwestern Saskatchewan owned and operated
by Cogema Resources Inc. (a majority owned subsidiary
of the French Atomic Energy Commission). The proposed
expansion of the TMF was first made public in
early spring 1998. This case is reviewed here
as an instructive as to how the AECB interprets
their responsibilities under the Canadian Environmental
Assessment Act (CEAA) in general, and "screenings"
in particular.
In 1993, the expansion of the
mining operations underwent a full environmental
assessment under the EARP Guidelines Order. The
Panel gave approval for construction and operation
of the proposed expansion. Cogema argued that
the existing TMF had enough capacity to handle
the tailings that would result from the expansion.
The Panel accepted this argument but also stated
that this TMF should be closed as soon as possible.
In the spring of 1998, Cogema
made known their intent to expand the TMF because
they had at least ten more years of reserves and
not enough capacity in the TMF. As the responsible
authority, the AECB received the information as
part of Cogema’s request for a licence renewal.
The provincial government and the AECB jointly
prepared guidelines for an Environmental Impact
Statement.
In almost all circumstances,
the AECB under the CEAA’s Section 20 generally
used subsection 20 (1) (a) because "the project
is not likely to cause significant adverse environmental
effects." In this instance, a more honest interpretation
of the Act would have been sub-section 20 (1)
(c) (I) which says "where it is uncertain whether
the project, ... is likely to cause significant
adverse environmental effects" There was no question
that the expansion of the TMF and the concomitant
increase of production of uranium would fall under
sub-section 20 (1) (c) due to serious concerns
about the effects of leaching radionuclides.
Furthermore, due to the fact
that there would be an increase in production
of uranium, this project would automatically come
under the Comprehensive Study List. Although the
AECB attempted to interpret the Act in the most
narrow possible fashion, evidence for production
exceeding a 35% increase submitted by Maisie Shiell
(July 13, 1998) clearly pointed to either a Comprehensive
Study Review or to referral to the Minister. The
AECB gave a weak response by saying they had not
made a decision yet on what kind of EA would be
required. Neither were undertaken as Cogema soon
after announced the closure of this mine.
Eventually, Cogema ceased the
preparation of an EIS as they announced on August
20, 1998 that they were going to suspend their
Cluff Lake Operations in December 2000.
Key Issues
The Need for Public Participation:
The public is regularly kept
out of the environmental assessment process when
the AECB is the responsible authority. When a
screening report is issued by the AECB, it is
made public as part of their submissions to the
Board when licensing decisions are to be made.
AECB staff do not solicit public input during
the screening process. The public is able to read
their reports only during the actual licensing
process and has to argue with the AECB over interpretations
of the Act in terms of the kind of assessments
required.
Need for Clarity:
In order to alleviate differences
of interpretation between the AECB and the public,
the Act must be much clearer; aided by better
definitions of terms and direction from the Canadian
Environmental Assessment Agency. ‘Interpretive
leniency’ the AECB used (and uses) allows them
to avoid making commitments to the public review
of projects. The goal should be finding ways to
create easy access for people to become involved.
Such narrow interpretations of
the Act and scoped implementation are common for
the AECB. A further example of this is from the
Screening Report dated June 2, 1998 for the Tritium
Target at the Electron LINAC research Accelerator
Facility at the University of Saskatchewan. There
had been a major release of radium into a nearby
lake the previous year. The AECB Staff were quite
concerned about this release as it was unclear
what the reasons for the release were, what was
the source of the contamination or what the effects
on the biota would be. The Board Staff, as part
of their duties in preparing a recommendation
to the board on whether or not to grant a new
operating licence, undertook an environmental
assessment screening. The public was not notified
of this activity and only saw the report when
it was released as an appendix to their submission
to the Board which recommended approval of the
operating licence, albeit for only nine months.

3.0 Comprehensive Studies
The TransQuebec and Maritimes
(TQM) Portland Natural Gas Transmission System
(PNGTS) Extension Gas Pipeline Project
Overview
The project was justified in
terms of the need for additional capacity to deliver
Western Canadian gas to the northeastern States.
It called for the installation of some 210 km
of 600 mm (24 inch) pipeline from TQM’s existing
system at Lachenaie to a point on the Quebec –
New Hampshire border near East Hereford. The proposed
pipeline route involved over 200 watercourse crossings,
twelve of which were large rivers, including three
channels of the Saint Lawrence. The majority of
these large river crossings would be performed
by directional drilling. Some 48% of the route
was on cultivated land and 35% throughout wooded
areas. 55% of the route would be adjacent to existing
linear infrastructures such as roads, power lines,
and pipelines. The Environmental Assessment under
the Canadian Environmental Assessment Act (CEAA)
was triggered through the law list (approval by
the National Energy Board under its Act) and a
comprehensive study was required (pipeline more
than 75 km in length on a new right of way).
The project went through proponent
information meetings followed by public hearings
under the Quebec Bureau d’audiences publiques
sur l’environnement (bureau of public hearings
on the environment) (BAPE), the Commission
de protection du territoire agricole du Quebec
(Quebec agricultural land protection commission)
(CPTAQ) and the National Energy Board (NEB or
Board). Finally, there were also detailed route
hearings in cases where property owners objected
to the pipeline route across their land.
Under the BAPE process, the proponent’s
impact study was made public 9 May 1997. Starting
9 June 1997, a panel of three was given the statutory
four month mandate to hold public hearings and
produce a report on its findings for consideration
by the Quebec Minister of the Environment and
decision by the Quebec Cabinet of Ministers. Eight
documentation centers were set up and two rounds
of hearings held, the first for questions and
the second for opinions, at four locations along
the pipeline route. Quebec approval for the project
came in December, just as the NEB hearings were
finished.
For Mouvement Au Courant (MAC),
the BAPE hearing opened many new avenues of questions
regarding, in particular, the start and finish
points for the pipeline that the proponent considered
as fixed. They found out later that there had
already been much discussion on that issue in
a previous hearing before the NEB and, in camera,
before the Quebec Regie du gaz naturel,
who gave pre-authorization for the project in
September 1996. MAC also discovered that the United
States portion of the proposed pipeline had already
been summarily dismissed when the Federal Energy
Regulatory Commission (FREC), responsible for
authorizing PNGTS, published its Draft Environmental
Impact Statement (EIS) in June 1997; a Vermont
crossing point was favoured over the proposed
one in New Hampshire.
The NEB’s public participation
process started, for the initiated, with requests
for comments on the scoping package, which included
topics to be covered under the NEB Act and CEAA.
With some knowledge that there were various alternatives
other than the proposed project, MAC requested
that the scope of the EA be broadened to include
a detailed analysis and comparison of alternatives.
Four pre-hearing information
seminars were held regarding the Board and its
role, the various applicable law and regulations
(with handouts) and on how to intervene as either
a "Full Participant" throughout the whole quasi-judicial
proceedings, or as a "Limited Participant" (mainly
for affected property owners). Seven documentation
centers were established. A panel of three Board
members held 19 hearings, with simultaneous translation,
during November and December 1997 in Montreal
and Orford and transcripts were made available
to intervenors who could not afford to purchase
them. The panel heard extensive evidence on the
choice of the border crossing point, technical
feasibility, convenience, cost and environmental
impacts, with particular attention to dynamiting
damage to underground water sources, use of the
right of way by snowmobiles and all-terrain vehicles,
possible pipeline rupture and damage to areas
of special ecological value.
Within the context of the Board’s
regulatory powers on rates, there was much debate
on alternatives that would be shorter and thus
cheaper and less environmentally detrimental.
The debate was spearheaded by Union Gas, who paid
the lion’s share of gas transmission fees to TransCanada
Pipelines (TCPL) and TQM. However, the proponent
was not obliged by the panel to present a detailed
analysis of the most feasible alternative, which
would generally follow the existing Montreal –
Portland oil pipeline through Vermont rather than
New Hampshire and would cut approximately 70 km
off the length of pipeline in Quebec.
To the surprise of many, the
panel chose to ignore completely the evidence
of alternatives, arguing that the project was
not likely to have significant environmental effects.
The panel soon after released its Comprehensive
Study Report (CSR) at the end of February 1998,
concluding that the project was acceptable. Despite
calls for an independent panel hearing on the
project, the Federal Minister of the Environment,
at the end of March, agreed with the CSR conclusions
and referred the project back to the NEB for final
decision, which followed immediately.
As expected, the Board approved
the project and rejected Union’s idea that the
PNGTS Extension users should pay a surcharge based
on the extra cost over and above what a cheaper
alternative would have cost. On this last point,
Union requested that the Board review the decision
because it did not take into account all the evidence
heard by the panel. Union also initiated a judicial
review procedure before the Federal court of Appeal.
In June 1998, the Board reiterated its position
that it did not have to look in detail at alternatives
and, in February 1999, Union dropped its court
case.
Key Issues
Strengthening the Act:
Despite a good public participation
procedure, the outcome was disappointing because
the panel refused to consider all the evidence
before it. This is in part the fault of the Act
since it does not require the Proponent and the
Responsible Authority to search out the solution
with the least impact. To participants, it felt
in many ways as though the process was a ‘waste
of time’.
Panel Make-Up:
The panel could have been more
objective if it had not been made up solely of
NEB members.

4.0 Review Panels:
Oldman River Dam
Overview
A turning point with respect
to environmental assessment in Canada, the Oldman
River Dam established the right of the federal
government to play a significant and legislated
role in environmental management and decision-making
across the country. On a more local level, the
Oldman River Dam illustrates the damage that can
occur when projects are not assessed in a comprehensive,
proactive and transparent manner.
The Oldman River Dam is located
downstream from the confluence of the Oldman,
Crowsnest and Castle Rivers, all near Pincher
Creek in Southern Alberta. The dam is 76 meters
high and 3 0780 meters long and is an earth and
rockfill dam. At full supply level the reservoir
would store 490 million cubic meters of water,
extend 24 kms in length and have a surface area
of 24.2 square kms. The purpose of the Dam was
to "impound water for water management, flood
control, erosion control, flow regulation, conservation
and recreation". Proponents of the dam asserted
that flow regulation achieved by the Dam would
also permit irrigation expansion, enhance downstream
fisheries, improve water quality, provide an assured
water supply for municipal and other uses, and
provide Alberta with greater flexibility to meet
its commitments for water supply to downstream
Provinces.
Although the Oldman River Dam
Environmental Assessment was undertaken between
November 1990 and April 1992, the project had
a much longer history. In May of 1958, the government
of Alberta first approached the Prairie Farm Rehabilitation
Administration (PFRA) of the federal Department
of Agriculture to determine the feasibility of
constructing a storage reservoir on the Oldman
River at a site called Livingstone Gap. From this
date, numerous studies were undertaken by mixed
public and government panels and committees that
sought to ascertain the best sites and various
water supply and demand requirements of the region.
Although several of the studies pointed to serious
environmental concerns and in 1978 even recommended
against building the dam, in September, 1987 the
federal Minister decided to forego assessment
under the Environmental Assessment Review Process
Guidelines Order (EARPGO) and approved the application
to construct at the Three Rivers site.
Friends of the Oldman River (FOR),
a group of concerned citizens, was organized in
mid 1987 to oppose the project. After several
requests to the federal Minister of the Environment
for a Review were refused and after several unsuccessful
attempts to have the license withdrawn at the
provincial level, FOR took the matter to federal
court. There, on April 21, 1989, Justice Jerome
dismissed their application. In the meantime,
by March 31st, 1989, the dam construction
was already 40% complete.
Soon after, FOR appealed to the
Federal Court of Appeal and was successful, and
while the dam was nearing completion, a public
review was set up in the form of a Panel Review
Process. As the review of the Dam was carried
out while the construction of the dam reached
completion, the Panel did not prepare guidelines
nor was an Environmental Impact Statement prepared
by the proponent of the project. Instead, the
Panel, with the help of provincial resource people
and interested citizens, prepared an Additional
Information Requirements document. The public
were involved in a series of "Issue Identification
Meetings" held in January of 1991. Following this,
a team of technical specialists to the Panel and
federal, provincial and local resource people
prepared a response to the Additional Information
Requirements document. This collection of
responses guided the discussion at further public
meetings and hearings.
The panel stated that "although
many environmental and socioeconomic impacts are
discussed in this report, the major considerations
are those affecting fisheries, wildlife and riparian
forest ecosystems, and those affecting the Peigan
Indian Band". The panel found that the impacts
in these four areas were of such significance
that they far outweighed the marginal economic
benefits derived from increased irrigation, agriculture,
and other uses of the dam. This lead the panel
to its first recommendation to decommission the
dam by opening the low level diversion tunnels
to allow the unimpeded flow of the river. All
but one panel member agreed with this primary
recommendation.
Key Issues
In its final panel report to
the Federal Minister of Environment, panel members
put forward some strongly worded comments regarding
the project and, more specifically, the assessment
process.
Timing of Review:
A key principle of effective
environmental assessment lies in its timely application.
An effective assessment must take place before
any irrevocable decisions are made. This was clearly
not the case in the Oldman River Dam, and the
panel commented on the fact that, by the time
the federal government convened the panel, many
people were wary of spending more taxpayers’ money
on a project that had already been "studied to
death" and was virtually built. If an assessment
is integrated into the early planning phase of
a project, more thought can be given to a consideration
of the need of the project, purpose of the project
and potential impacts of the project. This saves
both time and money for the government, the proponent
and the taxpayers.
On-going Construction during
the Review:
The credibility of the review
process would have been augmented by a cessation
of construction on the dam. Again, this comment
touches on the idea of irrevocable decisions being
made before an environmental assessment is completed.
The panel went on to recommend that, if a project
commences before the process is implemented, the
federal government must use statutory power to
halt construction of the project and, failing
this, the Minster of the Environment should use
all available statutory power to implement accepted
Panel recommendations.
Despite the lateness of the panel
review, it is widely recognized that the panel
resulted in the Oldman River Dam being a much
better project. Despite the fact that the need
for the project was never established and continually
questioned, the panel’s recommendations, which
numbered into the twenties, offered sound solutions
for the mitigation of already apparent negative
impacts of the project. However, like other panel
reviews, the recommendations were only recommendations
and not binding on the federal government.
Uranium Mine Tailings Decommissioning
Overview
In February, 1993 the Atomic
Energy Control Board referred the decommissioning
of Rio Algom and Denison's uranium mine tailings
at the Quirk, Panel and Denison waste management
areas to the Minister of the Environment, requesting
a review under the Federal Environmental Assessment
Review Process Guidelines Order (EARPGO). Scoping
sessions were held in December 1993, draft guidelines
were issued and the Environmental Impact Statements
were released, with comments on their ability
to meet the guidelines required, in February 1995.
A hearing was held in Elliot Lake in November
1995, and continued into January 1996 (they had
been scheduled to conclude in November, but the
death of a Serpent River First Nation elder required
that the community hearing in Cutler, the Serpent
River First Nation community, be delayed until
January).
Rio Algom Ltd. and Denison Mines
Ltd. had requested authorization from the Atomic
Energy Control Board (AECB) to decommission the
tailings management areas of their uranium mines
in the region of Elliot Lake, Ontario. The companies
had been authorized by AECB to recover material
and to demolish surface structures and underground
work sites. Given the similarities and possible
environmental interaction between the two companies’
tailings management areas, the AECB had recommended
that the panel be mandated to examine all currently
licenced tailings areas, but the review did not
include the 8 remaining unlicensed tailings areas.
Rio Algom and Denison Mines were
proposing to decommission the tailings areas by
constructing a series of dams and dikes to flood
the tailings. By providing a protective water
barrier, such a ‘water-submersion’ technique was
purported to drastically reduce acid generation
by acting as a barrier to oxygen reaching the
tailings and by also acting as a barrier to radon
gas escape.
A three person panel was appointed
by the Minister of the Environment, two with mining
experience in the region and associated with the
mining industry, and the third - the panel chair
- a retired federal civil servant. The two companies
- Rio Algom and Denison - had jointly retained
the consulting firms of Senes Limited and Golders,
two engineering firms. Various presentations were
made by the Atomic Energy Control Board, Health
Canada, Environment Canada, Ontario’s Ministry
of Northern Development and Mines and the City
of Elliot Lake. Numerous local member groups,
including Serpent River First Nation, and out-of-region
environmental and women’s organizations, made
submissions while Northwatch was the single consistent
public interest participant.
Northwatch's key concerns with
respect to the uranium mine tailings in the Elliot
Lake basin could be grouped under three categories:
1) Radiological affects: Exposure to ionizing
radiation can cause biological damage. Damage
from radiation is cumulative. Several major reports
have indicated that Canadian standards should
be improved; 2) Acid generation: The exposure
of sulphide-bearing minerals to air and water
creates sulphuric acid. Acid generation can last
for decades, centuries or even longer, and its
impacts can travel many miles downstream; 3) Cumulative
impacts on the social and environmental well-being
of the basin. The residents of the Serpent River
basin - both human and non-human - have a basic
right to a healthy habitat and water source, both
of which could be adversely impacted by the tailings
and their inadequate management. Thus, the management
decisions affect the lifestyle, life choices and
very life blood of the Serpent River basin. Northwatch
believed that the Review failed to address each
of these issues adequately.
The panel report concluded
with an approval of the undertaking in June 1996,
but with several key conditions, including the
recognition of the need for perpetual care, a
call for a public monitoring body, and support
for curiosity-driven research in the area. The
government response was issued almost a year later,
and it effectively rejected the Panel’s key recommendations
as having been outside their mandate, with the
exception of the Panel’s recommendations to accept
shallow water cover as the preferred decommissioning
option. The Atomic Energy Control Board has subsequently
granted a license for the decommissioning of the
Stanrock tailings management area, and were considering
(in February 1999) an application for the decommissioning
of the Denison TMA 1 and TMA 2 waste sites.
Key Issues
Terms of Reference:
Initially, the terms of reference
excluded cumulative effects, but after effective
interventions by First Nations, environmental
organizations and the provincial government, the
terms of reference were slightly broadened to
give consideration to the contribution of the
mines under review to the cumulative effects in
the Serpent River basin. The review would have
been improved by making this broader to include
cumulative effects in the Serpent River basin
more generally, and by requiring the proponent
to have addressed it more directly and comprehensively.
EIS Deficiencies:
The EIS was deficient in
its investigation of key areas related to acid
mine drainage and physical or structural concerns
related to the proposals. Even more important
however were the deficiencies in addressing radiological
effects and related concerns. A number of difficulties
were presented by the structure and form of the
Environmental Impact Statements; difficulties
which made a review challenging to the point of
being unduly onerous.
Participant Funding:
Participant funding was inadequate
to the task, particularly given the range of technical,
environmental and health concerns.
AECB:
The role of AECB was too
multi-faceted in their participation as intervenor,
as a former regulator having eliminated the most
environmentally sound option prior to the start
of the review and as the future regulator who
would ultimately grant the licenses. (Note: AECB
had already granted a license to decommission
the surface structures and mine workings; this
had resulted in construction debris being placed
in the mine shafts, effectively eliminating the
environmentally soundest option of returning 30-50%
of the tailings to the underground workings).
Scope:
A number of other sites were
excluded through a procedural definition rather
than a practical reason. The review looked at
only those sites that were still under license
by the AECB.
Notice:
Notice was both limited and
late for the review commencement and the scoping
sessions.
Decision:
The government response rejected
the key panel conclusions which would have been
of benefit to the community and the environment.
Nuclear Fuel Waste Management
Overview
Atomic Energy of Canada Limited
is a crown corporation which the federal government
funds to research and promote nuclear technologies.
AECL has, for decades, been trying to find a means
to rid the nuclear industries of their biggest
technical and public relations problem – the highly
radioactive wastes produced by nuclear reactors.
In 1988, the AECL "concept" of a "disposal" method
for nuclear fuel wastes was made the subject of
a federal environmental assessment review under
the Environmental Assessment Review Process Guidelines
Order (EARPGO). While described by the federal
government as being a product of a "Canada-Ontario
Program" on nuclear fuel waste, the review process
itself was strictly a creature of EARPGO, and
lacked any of the distinguishing features of the
Ontario Environmental Assessment Act as it was
in effect at the time of the review (eg. intervenor
funding, notice provisions, evidentiary procedures).
Additionally, the Ontario government was not represented
at any point in the proceedings, nor did it make
appointments to the Panel or the Scientific Review
Group established to assist the Panel with technical
advice.
The AECL concept was to bury
the highly radioactive nuclear fuel waste in the
granite rock of northern Ontario. This "concept"
was the result of political decisions in the 1970's,
and was not the subject of a public or scientific
review before the federal government adopted it
as policy. The approval that was being sought
by AECL was for the "concept" only, and did not
require that AECL identify a site or prove that
it would not cause harm where it was eventually
to be located. By the end of the eight year public
process, they were still undecided as to
specifics such as site location and disposal method.
The AECL concept was referred
to the Minister of Environment by the Minister
of Energy, Mines and Resources in 1988, and a
Panel was appointed the same year. The Panel held
scoping hearings in 1990, and issued guidelines
for an Environmental Impact Statement in 1992.
AECL released its Environmental Impact Statement
in the spring of 1994, and a nine month review
period concluded with the Panel acknowledging
the deficiencies of the EIS but refusing to issue
a deficiency statement. Instead, the directed
AECL to provide additional information, but did
not require that it be provided until after the
hearing had begun. The hearing was held in three
phases (general, technical and community) from
March 1995 to March 1996.
The environmental assessment
review process included an eight member Panel
and an equally sized Scientific Review Group,
each appointed by the federal panel. There were
a number of changes in Panel membership, most
notably the resignation of a panel member between
the first and second phases of the hearing, which
was informally reported as being due to disagreements
with either agency staff or the generally accepted
protocol of not expressing personal views during
hearing sessions.
The "responsible authority" Natural
Resources Canada (initially Energy, Mines and
Resources), maintained a constant presence throughout
the hearing, and presented on several occasions,
including on the final day of the technical sessions.
There, director of Uranium and Fuel Waste Division
Peter Brown presented NRCan’s "Nuclear Waste Policy
Framework", a document which had been developed
with only nuclear industry input. Environment
Canada, regrettably, was absent from the process,
with the exception of some very well prepared
and comprehensive comments submitted during the
review scoping exercise that identified a strong
and productive role for Environment Canada which
was never fulfilled. Atomic Energy Control Board
staff were consistent participants and conducted
themselves in a relatively neutral manner overall,
raising relevant technical issues and concerns.
Ontario Hydro was a key player, acting as co-proponent
through much of the hearing and offering themselves
as the future "implementing" agency from the first
week of the hearing. Other organizations, such
as the nuclear industry associations, the Royal
Society and various professional groups associated
with the nuclear industry, also participated.
Each voiced similar support for the nuclear industry
and expanded use of nuclear power.
The public interest was represented
by a variety of church, women’s, environmental,
youth and peace organizations. These participants
were vastly outnumbered by proponents particularly
at the"roundtable" discussions convened by the
Panel in the Phase I hearings. The sessions were
also unrecorded, and considered by many public
participants to be lacking in either fairness
or accountability. In the phase III hearings,
hundreds of presentations were made in 17 communities
from Saskatchewan to New Brunswick, where the
general public outnumbered the nuclear industry
several fold.
In March 1997 the Federal Review
Panel issued its reports. Its key conclusions:
AECL had failed to prove that the "concept" of
burying nuclear waste in the Canadian Shield was
safe or acceptable. In brief, the Panel found
that the AECL concept was still just that - a
concept, with some theoretical possibilities,
but with no demonstration of safety or acceptability
in a real-world analysis. The Panel made a number
of recommendations, all of which emphasized the
need for a strong public role in future development
and evaluation of nuclear waste management options
and the necessity of developing a social and ethical
framework for use in assessing options. The Panel
recommended that an independent agency be established
with a board of directors with broad representation,
and that the waste management option must gain
broad acceptability before any search for sites
begins.
The government quietly released
its response to the panel report in December 1998.
The 17-page response rejected the Panel conclusions
in a number of key areas. The government announced
that it would create a new agency, but its board
of directors would be made up only of nuclear
industry representatives. Public involvement in
evaluating nuclear waste management options would
be restricted, and discussions with communities
in "siting territories" could begin immediately
as part of "building acceptability" for a waste
management option (rather than following broad
public acceptance as the review panel had recommended).
Perhaps the most revealing aspect of the government
response - and the most damning - was its repeated
declarations that acceptance of a nuclear waste
management option will "support nuclear energy,
and particularly the CANDU option, as a sustainable
supply option for electricity". The future of
the nuclear industry was specifically excluded
from the 10-year review. Securing the nuclear
industry’s future is the priority message in the
government response.
Key Issues
CEAA Communications:
Having transcripts available
electronically (through CEAA) allowed a broader
group to follow the hearings in a detailed manner,
allowing some to make particularly effective interventions
during the final phase of the hearings.
Terms of Reference:
The terms of reference specifically
excluded any discussion of energy policy - the
continued production of nuclear industry - and
any discussion of military use of nuclear technology.
These were key and central questions; a separate
review on energy policies was announced as a "parallel"
process at the time of the review’s announcement,
but was begun and cancelled in 1990 with no discussion
having taken place.
EIS Deficiencies:
The EIS was deficient, and acknowledged
as such by the Panel, but the deficiencies were
not addressed before the hearing began; this not
only was a perversion of the EARPGO process, but
created problems within the review process.
Participant Funding:
Participant funding was grievously
inadequate. Funds were awarded for scoping and
then for the hearing itself, but in the second
instance, the funding committee - with no explanation
provided - allocated only a portion of the available
funds, despite the requests exceeding the available
amount several fold. Advance preparation and planning
were made very difficult, especially when the
funds were then allocated in a third round of
funding.
Rules of Evidence:
The proponent frequently filed
new or differently presented information on the
very day of its examination in the technical hearings.
There were seldom enough copies for all of the
intervenors, making it more difficult for intervenors
to examine the evidence or to prepare questions.
The proponent was required to indicate only in
very broad terms what evidence they would be presenting,
and documents and oral presentations/responses
frequently relied on documents which were not
available.
Notice and Access:
The Agency relied almost exclusively
on a limited mailing list for providing notice
about the review, and in the period between scoping
and the hearings, removed a large number of participants
from their mailing list. Newspaper advertising
was limited, and community mechanisms for providing
public notice were not generally utilized. Phase
I and Phase II hearing were held in Toronto, outside
the area of the undertaking, resulting in limited
access to those most likely to be affected by
the outcome. All Phase I and Phase II sessions
were held during the day, further limiting public
access to those able to take time away from their
workplace. The limited funds provided through
the Participant Funding demanded that groups limit
their participation in Phase I and Phase II sessions
to one representative, often for only some of
the sessions.
Time Allocations:
Presentations by the public participants
were limited in time (20 minutes in Phase I, 15
minutes in Phase II, and 10 minutes in Phase III),
requiring participants to limit their comments
and prioritize issues to be addressed. This was
particularly of concern in Phase II, where there
were a large number of complex and critical issues
to be addressed, and organizations could only
afford to have one representative (at most) in
attendance, so all issues had to be addressed
in only 15 minutes.
SRG Constraints:
A Scientific Review Group was
established to provide technical advice to the
Panel, but had been directed to limit remarks
to its terms of reference, which excluded social,
ethical or economic issues. This placed the SRG
in the position of having to abstain from remarking
on what they had identified as a key issue in
the "concepts" achievability, i.e. costs and financial
estimates.
Decision:
The government response rejected
the key panel conclusions.
The Environmental Assessment
of McClean Lake
Overview
The fundamental recommendation
of the Report of the Joint Federal-Provincial
Panel on McClean Lake, Saskatchewan, upon which
all other recommendations were hinged, called
for the Cogema’s McClean Lake Mining Project to
be delayed five years. The Panel's reasoning was
based on the need to obtain more experience with
previous tailings management facilities in the
surrounding area and more comprehensive community
health information. The delay would also allow
employment opportunities for Northerners to be
maximized through increased training and education
efforts, provide greater opportunity for further
discussion of the larger ethical/environmental
issues surrounding uranium mining, and allow more
time to assess the cumulative biophysical and
socio-economic impacts (Joint Federal-Provincial
Panel Report, 1993:41).
The federal and provincial governments,
as well as the Atomic Energy Control Board (AECB)
repeatedly ignored the recommended five-year delay.
Despite both the Panel's and the public's criticism
of Cogema's failure to provide an adequate tailings
disposal plan, the AECB began considering granting
Cogema a license to begin constructing the JEB
pit tailings management facility at McClean Lake
for the summer of 1998.
On February 2nd, 1999,
after several routine inspections revealed major
flaws in the filer rock at the tailings management
facility, the AECB informed Phillip Penna of the
Inter-Church Uranium Committee (ICUC) that it
was "highly unlikely" the McCLean Lake project
would be licenced at the February 24, 1999 AECB
Board Meeting.
Key Issues
Before approval, conditions
need to be set:
Before a uranium mine receives
overall government approval the Review Panel's
recommendations must be met. Where serious environmental,
health and ethical concerns abound, such as those
identified by the McClean Lake Joint Panel, they
must be dealt with prior to the mine receiving
overall approval.
Revenue Sharing Recommendations
not implemented by governments:
One of the Panel's conditions
for mine approval after the five year moratorium
had expired was: "agreement on a form of revenue
sharing that is acceptable to the majority of
the impacted communities" (Joint Federal-Provincial
Panel, 1993:43).This condition of approval has
not been implemented.
Failure to follow Panel
Recommendations:
Governments and regulators are
not directly accountable to the environmental
assessment review process and those who participate
in it. In approving the McClean Lake mine after
the panel recommended a five-year delay in mining,
the governments and AECB showed little respect
for the Review Panel’s findings or the public's
involvement in the process. As a consequence,
the public became unwilling to participate in
future Panels unless the Panel recommendations
were implemented.
Need for strong regulation
of uranium industry:
There is a heavy onus on governmental
regulatory systems to ensure safety and environmental
protection in the uranium industry. This responsibility
is problematic due to the current lack of political
will to impose regulatory restrictions on economic
development activities at both levels of government
(Saskatchewan Environmental Society, 1998). As
both federal and provincial governments downsize
their environmental protection capacities, regulatory
monitoring and enforcement capacities are reduced,
and consequently, could lessen governments' and
the public's knowledge of whether proper mitigation
measures and safety precautions at tailing sites
are implemented and performing to proper standards.
Critical issues surrounding
uranium mining/production:
Cogema is 90% owned by the French
Atomic Energy Agency, the agency responsible for
French nuclear weapons production and testing.
During environmental assessments of all uranium
mines in Northern Saskatchewan both levels of
government continually declared that a discussion
of the connection between uranium mining and nuclear
weapons is outside the mandate of the environmental
assessment panels. Governments have stuck to this
position despite the fact that every report they
received from a Panel raised serious concerns
about the nuclear weapons issue. Such concerns
should be within the terms of reference.
Tailings Facility incompetence:
Cogema has failed to provide
an adequate tailings disposal plan for the McClean
Lake Mine. Cogema's failure in this regard is
clearly seen in the review of the Cigar Lake and
Midwest proposals. With the magnitude of long-term
health and environmental impacts involved in uranium
mining, Cogema's regulatory indifference and lack
of technical competence to construct and maintain
adequate tailings facilities should be sounding
the alarm to governments that mine approval must
be based on Panels' findings and not political
expediency. Unfortunately, this is not the case
at present.
Long-term responsibility:
Because of the long-term hazards
associated with uranium tailings, the mine site
at McClean Lake requires monitoring long after
the mine has closed, far more than the currently
legislated corporate responsibility of fifteen
years after decommissioning. This clearly requires
long-term funding and the Panel outlined various
ways of ensuring these funds will be available.
Possibilities included insurance, performance
bonds, trust funds, or an irrevocable letter of
credit.
Cheviot Coal Mine
Overview
In March 1996, Cardinal River
Coals Ltd. (CRC) announced plans to develop a
large open-pit mine coal mine in the foothills
of the Rocky Mountains, just south of Hinton,
Alberta. The proposed mine area was 23 km by 3.5
km and was located just 2.8 km from Jasper National
Park, a United Nations World Heritage Site. CRC
required approval under both federal and provincial
law for the construction, operation and decommissioning
of the open-pit mine prior to development. This
led to a Joint Alberta Energy and Utilities Board
and Canadian Environmental Assessment Agency Review
Panel being established to perform the environmental
assessment. Despite serious gaps and implications
arising in the assessment process, such as CRC’s
failure to complete a cumulative effects assessment
and the Panel’s failure to exercise their legal
capacities under the Canadian Environmental Assessment
Act (CEAA) to have such an assessment completed,
the Panel recommended the project proceed. The
following analysis looks at some of the failures,
and successes, in the approval of the Cheviot
mine project. On October 2nd, 1997,
the Federal Government approved the Joint Panel’s
report on the Cheviot Project.
Key Issues
Requirements of the CEAA
must be satisfied during the Hearings Process:
CEAA requirements should not
be dealt with through permitting at the provincial
level. In the case of Cheviot, most environmental
impact assessments, all cumulative effects assessment,
and virtually all design and assessment of mitigation
measures were left to the provincial permitting
stage, and thus would be dealt with only after
the mine had been given overall approval. In the
Panel’s report this often resulted in monitoring
being passed-off as a replacement for doing the
assessments and planning mitigation. Recently,
the province of Alberta set-up two committees
to coordinate provincial permitting in accordance
with the Panel’s and the federal government’s
conditions, but the public still has no idea how
they are going to be heard, or what federal involvement
in the permitting will be. Despite a lack of public
input and transparency in the permitting process,
the province issued permits to build the transportation
corridor to the mine in December, 1997.
Crucial baseline information
had not been collected:
The baseline information crucial
to completing important environmental effects
assessments and cumulative impact assessments
had not been collected for the following areas:
water quality, minimum in-stream flow requirements,
Harlequin ducks, carnivores, and wildlife movement.
These areas of deficiency were identified by federal
and/or provincial agencies. In order for this
baseline information to be valid, it must be collected
before further disturbance occurs in the
area, and most certainly before a decision is
made on the present applications before the Alberta
Energy and Utility Board (AEUB).
Panel Failed to Complete
Cumulative Effects Assessment of Cheviot Project:
In its report the Joint Review
Panel stated that Cardinal River Coals Ltd. (CRC)
was unable to obtain the requisite information
from surrounding industries to complete a cumulative
environmental assessment (p. 56). This perception
of events was reiterated/confirmed by the federal
government in its response to the Panel’s report.
Under CEAA the Panel had a clear legal mandate
to obtain required information from neighbouring
developments in order to complete their cumulative
effects assessment (CEA). The Panel chose
not to complete a CEA. No CEA was completed despite
the fact that CRC owns the nearby Luscar mine,
and thus would – at the very least -- have the
information available to undertake a cumulative
effects assessment based on Luscar and Cheviot.
Again, the Panel chose not to pursue this possibility.
(Canadian Nature Federation 1997, 1998).
"Phased Cumulative
Effects Assessment" is not Cumulative Effects
Assessment:
The federal government acceptance
of the Panel’s position that cumulative effects
assessment could be undertaken in stages while
the project is developed was problematic, especially
in light of the fact that three federal departments
– Fisheries and Oceans, Environment and Parks
Canada – deemed the CEA of the Cheviot Project
inadequate during the Panel’s hearings. This seriously
compromised the importance of the "precautionary
principle" to sustainable development in Canada
– a stated purpose of the CEAA.
By accepting the Panel’s recommendation
to approve the Cheviot Project prior to knowing
the project’s cumulative environmental effects,
the federal government violated CEAA. In addition,
the federal government’s approval of the project
appeared to contain no mechanisms to: (I) halt
unacceptable cumulative effects if shown to occur;
and/or (II) enforce requirements to redesign or
abandon the project or phases of the project that
are resulting in unacceptable cumulative effects.
The idea that the cumulative
effects of a project can be evaluated while the
effects are occurring is highly problematic given
that the baseline conditions for effects evaluation
will be made of up dramatically shifting environmental
conditions (Canadian Nature Federation 1997, 1998).
Joint Panel for Cheviot
Environmental Assessment:
A process needs to be implemented
to ensure that the federal government appoints
the Chair of the Panel, or at least half of the
Panel members, in order to ensure the provisions
of CEAA are properly respected throughout the
assessment process. In the Cheviot case the Panel
was heavily weighted towards provincial interests.
On January 30th,
1998, in signing the Canada-wide Accord on Environmental
Harmonization and its sub-agreement on Environmental
Assessment, the federal government effectively
reigned in CEAA through devolving many of its
EA powers to the provinces. Accepting the Harmonization
sub-agreement on Environmental Assessment’s "single-window"
approach to EA, based on a "lead party" (Rodney
Northey) being responsible for the administration
of the assessment process according to their policies
and procedures (Section 4.3), the provinces were
allowed to largely determine their own EA process,
even where areas of federal responsibility (e.g.
fisheries) would be at stake.
This being said, the Joint
EA Panel at Cheviot was able to -- at least in
part -- counter the pro-development/anti-public
participation provisions inherent in the Alberta
Act. Under the public participation provisions
in CEAA, the public was able to get standing at
the Joint Panel EA hearings and thus more fully
participate in Cheviot EA. CEAA also provided
intervenor funding.
Alternatives to Open Pit
Mining at Cheviot Site not Considered:
Although required by Section
16 of Act, the Joint Panel’ review only looked
at other open pit mines in the Hinton area and
failed to look at alternatives such as moving
the Cheviot mine underground.
No Analysis of Public Need
for the Cheviot Project:
No social cost/benefit assessment
was done for the Cheviot mine. CRC refused to
provide such basic information as the threshold
volume of annual coal production needed to maintain
mine viability. In failing to fulfill the requirement
to look at alternatives to the project as required
under CEAA, the Panel clearly opted for the understanding
that energy development in Alberta is always in
the public interest (as outlined by the AEUB legislation).
Advanced access to information
for intervenors:
Intervenors were required to
submit information the day the hearing started,
barring the opportunity to counter the critical
information provided during the hearing itself.
Also, not enough time was given to intervenors
to prepare – only two months from the time the
Agency announced intervenor-funding to the time
of the hearing date.
Department of Fisheries
and Oceans’ Conditions for Permits:
The DFO failed to adequately
address fundamental questions such as "Is adequate
compensation possible?" and "Will additional mitigation
or redesign options be explored?" by relegating
concerns such as downstream effects of the mine
and its effects on the water quality to: 1) alternative
compensation strategies, and/or 2) monitoring
programs. It is unclear during the permitting
process whether CRC was obligated to develop additional
mitigation or redesign plans, except in the case
of water quality issues.
Failure of Federal obligations
under National Park Act to Protect Jasper National
Park:
In response to the Panel, the
federal government recognized the potential for
adverse effects on Jasper National Park and also
recognized that further information was needed
to determine the landscape conditions necessary
for the survival of grizzly bear populations dependent
on habitat within Jasper National Park and the
Cheviot mine area. Despite these statements, the
public was left with very little confidence in
the federal government’s protective capacity.
Failure to meet international
commitments:
Canada’s commitments to protect
biodiversity under the IUCN’s Global Biodiversity
Strategy, the Convention on Biological Diversity
and also its obligations under the World Heritage
Convention to protect the World Heritage values
of Jasper National Park, were threatened through
accepting the unmitigable damage to the habitat
of grizzlies, other large carnivores, and fisheries
represented in CRC’s development plan.
Smallboy Cree Not Allowed
Full Participation in Environmental Assessment:
During the Panel’s hearings,
the Smallboy Cree were not provided the opportunity
for proper participation. In anticipation they
would file a claim in the Cheviot area, the federal
crown prosecutor informed Department of Indian
and Northern Affairs officials that they should
not respond to questioning by representatives
of the Smallboy Cree.
BHP Diamond Mine
Overview
In December, 1994, the Department
of Indian Affairs and Northern Development (DIAND)
initiated an environmental review of the first
diamond mine in Canada. BHP Diamonds Inc. proposed
to develop the diamond mine in the Lac de Gras
area of the NWT, an area of unsettled and overlapping
land claims and a region where little industrial
development had previously occurred. The assessment
process was seen as important because the handling
of the BHP proposal would pave the way for a plethora
of other mining and associated infrastructure
projects. Sierra Legal Defence Fund lawyer, Larry
Reynolds, commented that "the standard set in
this review will significantly influence how mining
and other development proposals are handled in
the future."
The proposal included the draining
of lakes and deposition of more than a million
tonnes of tailings into a fragile arctic ecosystem.
Due to the potential for significant economic
benefits, combined with Aboriginal and environmental
concerns with the project, the proposal attracted
considerable attention in the North and throughout
Canada. After a technical NWT Water Board Hearing
in 1996 , BHP was issued a water license. By September
1997, after considerable correspondence, the DFO,
DOE and DIAND outlined numerous concerns with
BHP’s Environmental Management Plan. Subsequently
the DFO carried out an investigation into BHP’s
suspected violations of the Fisheries Act.
At the time of the BHP proposal,
the environmental assessment (EA) process was
in a state of transition in Canada. The project
was reviewed under the Environmental Assessment
and Review Process Guidelines Order (EARPGO),
however, the Canadian Environmental Assessment
Act replaced EARPGO soon thereafter. When
announcing the review, the Minister of the Environment
noted it would be conducted in the "spirit" of
the CEAA.
In some parts of the western
Northwest Territories, CEAA is likely to be replaced
by the Mackenzie Valley Resource Management
Act. Problems encountered during the transitional
phase from EARPGO to CEAA should be reviewed and
addressed now, so that constructive criticism
can lead to improvements in the evolving EA process.
Key Issues
The EA Process was unbalanced
and unfair:
There was: 1) insufficient funding
and expertise to prepare interventions; 2) insufficient
time during public hearings to present intervenor
evidence - just 15 minutes each; 3) inadequate
time to review some of the EIS data: intervenors
had only days to analyze the new data before the
hearings commenced.
The EA Process was not
credible:
There was: 1) a lack of an adequate
technical review. The Panel Chair declared it
was not a technical review and the Panel did not
retain independent expertise; 2) insufficient
time for presentations and questioning at the
technical sessions; 3) a lack of comprehensiveness
and rigour - the fundamental purpose of an EA
review 4) too little attention was paid to region-wide
cumulative effects, e.g., implications of this
project and others for ongoing land claims negotiations,
land selection, and protected areas, in light
of future development in this region.
Certainty in the EA process:
The opinion of many participants
was that the panel’s recommendations were too
general to be very helpful (CIRL, 1997). The Canadian
Arctic resources Committee (CARC) characterized
the recommendations as "weak and insipid." This
view was supported by the actions of the Minister
of DIAND, who later required that legally binding
agreements be worked out with BHP.
A second difficulty was that
the Panel Chair announced, during the course of
the BHP hearings, that the EA panel hearing was
not a technical review, per se. The question then
became, "If the BHP review was not intended to
examine technical aspects of the project, under
whose auspices and when will such a review take
place?" (CARC, 1996a).
Finally, there were a number
of supplementary agreements created outside of
the normal regulatory requirements, e.g., the
Environmental Agreement and IBAs. The establishment
of these agreements was at the Minister's discretion,
creating a great deal of uncertainty with the
process. Furthermore, without a statutory basis
for the Environmental Agreement, there was no
assurance that environmental protection would
be guaranteed. One of the requirements of the
Environmental Agreement was that BHP submitted
Environmental Management Plans (EMPs) for the
construction phase of their project by early February
1997. These plans, when reviewed by the federal
and territorial government, were revealed to have
several areas of weakness. Several problems were
identified even after revised plans were submitted
by BHP.
The necessity of establishing
and improving the rigour of EA reviews:
The CARC Review (1996b) pointed
out that papers prepared for the CEAA articulated
a narrow concept of efficiency, whereby a process
was deemed efficient if proposals were passed
through the permitting stage as expeditiously
as possible. The papers failed to take into account
social benefits. Also, if a proper technical review
were undertaken earlier in the process, BHP could
have demonstrated to the public that they 1) had
conducted the appropriate studies to identify
the impacts and 2) had plans in place regarding
the mitigation of the potential impacts. However,
by not doing this, the lack of a rigorous and
comprehensive environmental review resulted in
an inefficient use of BHP and government resources.
The government should protect
public, not industry interests:
Both federal and territorial
governments took a firm pro-development stance
from the outset. Kevin O’Reilly of CARC noted
that both DIAND and GNWT representatives said
they were in favour of the project on the opening
day of the hearings in Yellowknife. Some government
officials were of the opinion "that the rigour
of government’s technical review and public scrutiny
of the BHP project was in certain respects compromised
as a result of explicit or implicit policy directives
that government should not be putting obstacles
in the way of approval." (CIRL, 1997).
The government should play
a major role in the technical assessment process:
Typically, it is the role of
government to assess the project application.
However, some participants were of the opinion
that the most rigorous scrutiny of the application
was supplied by the interventions of the Dogribs
and their technical and legal advisors (CIRL,
1997).
Intervenor funding:
Intervenors did receive funding
for the EA Panel Review, however had it been known
that the EA panel was not conducting a technical
review, intervenor funding could have been focused
on the Water Board hearing, where funding was
not provided.
More resources should go
into government participation in all stages of
the EA process:
CARC rated the performance of
some federal departments during the EA review
as "appalling." However, it is also the opinion
of CARC that government downsizing should be seen
as the culprit for what is viewed as a declining
capability to regulate resource development in
the North. Even with independent monitoring bodies,
it is the responsibility of government to enforce
environmental regulations and to protect the public
interest.
Permits should not go ahead
without the required permits, approvals and compliance:
At the time that the land use
permit was issued the government had no information
from BHP on their monitoring programs, or mitigation
strategies for potential impacts occurring during
the construction phase. By the time BHP submitted
their Environmental Management Plan (EMP) for
the Construction Phase, construction was well
under way. The government should have demanded
that BHP get their revised plan submitt |